Council contractors commenced installation of a 2.5m wide footpath from Wellington St to Smith St, Molong South and East side of the road.
Works commenced Tuesday 3 October 2023.
Works are being delivered under two phases:
-
Phase 1 – from Wellington Street to Smith Street (along Philip Street), works will conclude at the existing footpath on the Smith Street end.
- Phase 2 – from Philip Street to Edward Street (along Smith Street), works will conclude at the existing footpath on the Edward Street end.